Project Overview

Condition led renewal and remodelling of a munitions Road and Rail Transfer facility at HMNB (Clyde)

Deterioration of the concrete embedded rails caused the facility to be withdrawn from operational service in 2011

Services Undertaken

Validation of the derived rail design (GRIP 3) and preparation of the detailed rail design (GRIP 4+5), for a fully concrete embedded depot operating as a road and rail transfer point

Permanent Way design, structural rail concrete slab design, buffer stop specification, bespoke concrete embedded turnout switch clearance and drainage design, rail signage specification and structure gauging analysis

Designs prepared in line with MOD Rail standards

Key Project Specifics

Ministry of Defence rail network

Road / Rail transfer facility

Fully concrete embedded depot

Renewal and remodelling of 5nr sidings

Loco shed, transfer shed and train wash

Track system concrete base / in-fill structural slab design

Bespoke embedded concrete switch clearance design

Strategic slab surface water run-off design

Bespoke turnout switch recess drainage design

Buffer stop specification and over-run assessments

Rail signage specification

Safety demarcation specification

Structure gauging analysis

Value Added by Novus Rail

Nominally £0.2million saving identified and agreed with all relevant stakeholders for utilising an enhanced type of embedded rail / turnout system without any detriment to operations, compliance, performance or safety