Project Overview
The objective of this project was to increase the capacity and efficiency of the new A4095 link road by installing a new underbridge and cycle underpass within an embankment
Locations
Bicester Underbridges
Services Undertaken
After completing the topographical survey this project was hit with delays due to the covid-19 pandemic however we managed to work remotely with the client and keep the design on track with the agreed project programme
Highly accurate traversing of the survey controls was undertaken prior to sliding the new bridges into position, as these were obviously a high risk activity
Both bridges were successfully built along side the existing railway tracks and slid into position during a 100hour blockade over Easter weekend 2021
Key Project Specifics
Topographical surveys
Track condition examinations
Track layout design
Track level design
3D design strings
Civil engineering design co-ordination
Track construction detailing
Structure gauging assessments
Pre-installation traverse surveys
Construction design (AFC)
Ongoing support throughout the construction phase
Value Added by Novus Rail
Able to adapt to the issues raised by the Covid-19 pandemic. Remote working and social distancing was put in place to keep the business running as close to normal as possible. This project demonstrated our flexibility and efficiency